Case Study 6

20% Turnaround Time Reduction

Recovered One Full Day of Production and Generated Approximately $1MM in Additional Annual EBITDA

The Challenge
 

A Fortune 100 chemical company engaged me to identify opportunities to reduce the duration of its annual maintenance turnaround at a major chemical manufacturing facility.

The plant's annual shutdown lasted five days. Because the operation was sold out, every additional day of downtime represented lost production and earnings.

During a pre-turnaround planning session, we identified the annual catalyst replacement process in four large tubular reactors as the critical path determining the overall shutdown duration.

Each reactor was approximately 24 feet in diameter and contained 57,100 tubes, each 30 feet long. Across the four reactors, more than 228,000 individual tubes required catalyst removal, inspection, precision recharging, verification, and closure.

A specialized contractor performed this highly labor-intensive operation. Each tube required an accurately weighed catalyst charge, careful loading using a vibrating feeder, verification of the final catalyst level, and confirmation that the tube had been completed.

The opportunity was clear: Reduce the cycle time of the critical-path operation without compromising safety, catalyst loading accuracy, or quality.
 

The Approach

Rather than focusing solely on accelerating the contractor's work, I examined the entire catalyst replacement process—including preparation, material handling, workstation design, staffing, and execution.

Working directly with the contractor's team, I applied Lean principles to redesign the operation around three priorities.
 

1. Eliminate Delays Before the Critical Path Begins

We identified the materials, tools, equipment, and workstations needed for catalyst charge preparation and arranged for them to be staged while other shutdown activities were underway.

This parallel preparation ensured that the catalyst loading operation could begin immediately after the reactor's upper head was removed, rather than consuming critical shutdown time setting up the work area.
 

2. Redesign Catalyst Preparation for Continuous Flow

We redesigned the catalyst preparation assembly line at the tube-sheet level.

The improved process organized catalyst removal from 55-gallon drums, precision weighing of individual 3.20-pound charges, packaging into three-liter plastic bags, and staging of prepared charges close to their point of use.

By separating charge preparation from tube loading and minimizing unnecessary material movement, we created a more efficient flow of accurately prepared catalyst charges to the installation teams.
 

3. Optimize Parallel Work Without Compromising Safety

We evaluated the available working area on the tube sheet and determined the number of two-person teams that could safely work in parallel.

This allowed the contractor to increase productive work while maintaining safe access, controlled work areas, and the required catalyst loading and verification procedures.
 

The Demonstrated Results

One Full Day Eliminated From the Annual Turnaround

The redesigned process reduced the catalyst replacement cycle time for each reactor by 20%.

Because catalyst replacement controlled the turnaround's critical path, the improvement shortened the overall annual shutdown from five days to four days.

  • 20% reduction in catalyst replacement cycle time.

  • 20% reduction in total annual turnaround duration.

  • One additional day of production recovered annually.

  • Approximately $1MM in additional annual EBITDA from recovered production at a sold-out facility.
     

The Leadership Lesson

The original turnaround duration was driven not simply by the technical requirements of catalyst replacement, but by how the work was organized, prepared, supplied, and executed.

By moving preparation activities off the critical path, improving material flow, and optimizing safe parallel execution, we eliminated an entire day of downtime without changing the fundamental catalyst replacement requirements.
 

The lesson: The fastest way to shorten a shutdown is often to redesign the work—not ask people to work faster.
 

Op X-MEN LLC — Turnaround Optimization Through Lean Thinking.